11. Related construction work authorized by a licence subclass in Schedule I, II or III must be carried out at the same time as work in that licence subclass.
The holder of a licence subclass may carry out construction work that is similar or related to work in the licence subclass, except work reserved exclusively for master pipe-mechanics and electrical contractors.
For the purposes of this Regulation, the work covered by the principle of versatility in work organization, provided for in section 4.0.1 of the Regulation respecting the vocational training of the workforce in the construction industry (chapter R-20, r. 8), is considered to be related construction work.
O.C. 314-2008, s. 11; S.Q. 2024, c. 19, s. 65.
11. Related construction work authorized by a licence subclass in Schedule I, II or III must be carried out at the same time as work in that licence subclass.
The holder of a licence subclass may carry out construction work that is similar or related to work in the licence subclass, except work reserved exclusively for master pipe-mechanics and electrical contractors.
O.C. 314-2008, s. 11.